Project Name:                   Kingrey North

 

Project Representatives:

                                           Mr. Mark Osswald
                                           2750 Crawford Rd.
                                           Brookville, OH 45309

                                         
Project Description

The Kingrey North Project is located in Perry Township, Sections 6 and 7.  It is approximately 3,896 feet long, drains 134 acres (watershed size), benefitting 30 parcels of land.  Construction was completed 7/1/85, at a cost of $11,180.08.  Cost share funds reduced that amount by $7,248.00.  The estimated cost to reconstruct this project today is $27,000.00.
Ditch maintenance plans for 2003 and project funding are as follows.

2003 Project Maintenance  

1. Ditch mowing.  Estimated cost $250.00

2. Replace 50 ft section of 15" tile.  Estimated cost $500.00.

2003 Maintenance Budget

   1/03 Fund Balance                $1862.26
   2003 Assessments                 $500.00
   2003 Expenses                       $750.00
   1/04 Fund Balance                 $1612.26